2025-07
2025 Franklin County Township Resurfacing Program
EBE Goal = 8%
Upgrading various sections of Franklin County township roadways, detailed within; with asphalt resurfacing, curb, and sidewalk replacement.
Engineer's Estimate = $5,095,953.05
| 04/15/2025 02:00 PM UTC |
2025-11
2025 General Bridge Maintenance Contract:
EBE Goal: 6%
Rehabilitating the Norton Road 6.33 Bridge over Hellbranch Run by installing approach slabs, upgrading the bridge railing, and installing a new concrete overlay. A new concrete overlay will be installed on the Hayden Run Road 3.37 Bridge over Hayden Run and the Hague Avenue 1.72 Bridge over Barbee Ditch.
ENG ESTIMATE = $558,768
| 04/15/2025 02:00 PM UTC |
Number | Deadline |
---|---|
2020-08
Mann Rd 0.50 over Tributary of Rocky Fork Creek (JEF-TR107-0.50) - Replacement of the existing concrete slab culvert with a new concrete box culvert and the other incidentals necessary to complete the work.
ENG ESTIMATE - $542,650.62
| 06/30/2020 06:00 PM UTC |
2020-04
Smothers at Harlem BMP Improvement
Reconstruction of the existing water quality and detention basin that provides storm-water management for the intersection of Smothers Road and Harlem Road
ENG ESTIMATE $112,827.48
| 06/23/2020 02:00 PM UTC |
2020-06
Upgrading 11.140 miles of various sections of Franklin County roadways, detailed within; with asphalt resurfacing and aggregate berm material.
ENG ESTIMATE $ 2,379,923.89
ENG ESTIMATE W/ALTERNATE $ 2,691,250.29
| 05/19/2020 06:30 PM UTC |
2020-05
Ridpath Rd 0.69 over Stanford Smith Ditch (JAC-TR270-0.69) - This project consists of upgrading 0.05 miles of Ridpath Road by replacing the existing bridge over Stanford Smith Ditch, providing new drainage structures, and minimal roadway approach improvements.
ENGINEER ESTIMATE - $276,561.15
| 05/19/2020 06:00 PM UTC |
2019-14
Reynoldsburg-New Albany Road at Clark State Road Improvements: Upgrading 0.34 miles of Reynoldsburg-New Albany Road and 0.19 miles of Clark State Road by constructing a modern roundabout at the intersection of Reynoldsburg-New Albany Road and Clark State Road. The project also includes the installation of a closed storm sewer system, waterline, street lighting, sidewalks, and various other improvements.
ENG ESTIMATE $2,845,999.20
| 05/12/2020 02:00 PM UTC |
2020-05
Ridpath Rd 0.69 over Stanford Smith Ditch (JAC-TR270-0.69) - This project consists of upgrading 0.05 miles of Ridpath Road by replacing the existing bridge over Stanford Smith Ditch, providing new drainage structures, and minimal roadway approach improvements.
ENGINEER ESTIMATE - $237,810
| 04/28/2020 06:00 PM UTC |
2019-18
Dublin-Granville Road over Rocky Fork Creek (FRA-CR546-12.90)
Replacement and widening of the existing bridge over Rocky Fork Creek including the addition of a shared use path over the bridge and approximately 270 feet of shared use path along the south side of Dublin-Granville Road.
ENG ESTIMATE - $1,196,999.83
| 04/07/2020 06:00 PM UTC |
2019-15
Alum Creek Drive & Rohr Road Improvements: This project consists of the addition of right and left turn lanes at the intersection of Alum Creek Drive and Rohr Road, the addition of a second eastbound lane on Rohr Road from Alum Creek Drive to Port Road, a new signal installation at Alum Creek Drive at Rohr Road , pavement resurfacing, storm sewer and necessary traffic control devices.
ENGINEER'S ESTIMATE: $3,358,178.56
| 03/31/2020 02:00 PM UTC |
2019-21
Hayden Run Central Ohio Greenways Trail Improvements -
This project consists of constructing a missing Shared Use Path segment of the Hayden Run Central Ohio Greenways Trail between the City of Hilliard Corp Line and the City of Columbus Corp Line. The proposed limits extend under I-270. This project also includes pavement resurfacing, Hayden Run Road structure rehabilitation, and guardrail replacement.
ENG ESTIMATE = $821,960.90
| 03/10/2020 02:00 PM UTC |
2020-01
2020 - 2021 Guardrail Repair and Upgrade Program
ENG ESTIMATE $342,650.75
| 03/10/2020 02:00 PM UTC |