2025-003 2025 Residential Paving Program
Project: 2025 Residential Paving Program
Contract ID: 2025-003
Planning Engineer: Goodhue Consulting
Location: Wilmington, OH
Project Deadline: November 30, 2025
Overview: The proposed project includes resurfacing six residential streets totaling 4,765 feet, 6,320 feet of the Luther E. Warren multi-use path, and full-depth pavement patches through the City. The roadways to be resurfaced are: Fairland Avenue, Louise Street, Kathryn Drive, Hiatt Avenue, Kelly Drive, and Jenny Lane.
| 04/16/2025 04:00 PM UTC |
Number | Deadline |
---|---|
2025-002 Landfill Phase 9 Construction Project
Project: Landfill Phase 9 Construction Project
Contract ID: 2025-002
Planning Engineer: Terracon Consultants, Inc. -Mo Finy
Location: 397 S. Nelson Ave. Wilmington OH 45177
Project Deadline: August 21, 2025
Pre-Bid Meeting: Wednesday, February 12, 2025 @ 10 a.m. - On site
Overview: The proposed project includes construction of perimeter and interphase separation berms, composite liner system, and sedimentation pond. Prospective bidders should have 5 or more years of demonstrated experience in landfill cell and cap construction.
| 03/14/2025 07:00 PM UTC |
2025-001 RFP Emergency Water Construction Services
Project: RFP Emergency Water Construction Services
Contract ID: 2025-001
Overview: The City of Wilmington is seeking qualified consultants to provide timely remedy in the event of a water infrastructure related failure. The work shall include furnishing all materials, labor, equipment, and supplies necessary to provide emergency excavations, temporary restorations, and pipe repair services for the City of Wilmington.
| 01/08/2025 05:00 PM UTC |
2024-003 South Street Repaving And Improvements
Project: SOUTH STREET REPAVING AND IMPROVEMENTS
Contract ID: 2024-003
Planning Engineer: Paul Goodhue, P.E., PTOE
Location: South Street, Downtown Wilmington OH
Project Deadline: June 30, 2025
MANDATORY Pre-Bid Meeting: Wednesday, October 23, 2024 @ 12:30 p.m. at the Rick Moyer Community Room, City of Wilmington Municipal Building, 69 N South St. Wilmington OH 45177.
Overview: The SOUTH STREET REPAVING AND IMPROVEMENTS project includes curb and sidewalk replacement along South Street (US-68) between Main Street and Locust Street. Resurface South Street between Main Street and Columbus Street. Install storm sewer between alleyway north of Locust Street and Columbus Street along South Street.
ENGINEER'S ESTIMATE: $349,663.44 -Base, $30,756.96- Alternate
| 11/06/2024 04:00 PM UTC |
2024-004 Landfill Bridge Over Lytle Creek
Project: Landfill Bridge Over Lytle Creek
Contract ID: 2024-004
Criteria Engineer: Fishbeck, Thompson, Carr & Huber, Inc.
Location: Wilmington OH Landfill 397 S Nelson Ave Wilmington OH 45177
Project Deadline: May 23, 2025
MANDATORY Pre-Bid Meeting: Monday, Sept 30, 2024 @ 11:00 a.m. - at the Wilmington Landfill
Overview: This is a design-build project that consists of engineering and constructing a new bridge on a new foundation over Lytle Creek. Bridge is intended for use by heavy equipment.
Engineer's Estimate $504,366.00
| 10/25/2024 04:00 PM UTC |
2024-005 Main Street Paving Repairs
Project: Main Street Paving Repairs
Contract ID: 2024-005
Planning Engineer: Goodhue Consulting, Inc.
Location: W. Main Street, Wilmington
Project Deadline: November 30, 2024
Mandatory Pre-Bid Meeting: Thurs, Sept 26, 2024 @ 12:00 p.m. - Moyer Community Room, Wilmington Municipal Building 69 N. South St Wilmington OH 45177
Overview: The project includes pavements patches along W. Main Street between Nelson Avenue and Wall Street.
Engineer's Estimate: $194,825.75
| 10/07/2024 04:00 PM UTC |
2024-003 South Street Repaving And Improvements
Project: SOUTH STREET REPAVING AND IMPROVEMENTS
Contract ID: 2024-003
Planning Engineer: Paul Goodhue, P.E., PTOE
Location: South Street, Downtown Wilmington OH
Project Deadline: November 30, 2024
MANDATORY Pre-Bid Meeting: Thurs, Sept 19, 2024 @ 3:00 p.m. at the Rick Moyer Community Room, City of Wilmington Municipal Building, 69 N South St. Wilmington OH 45177.
Overview: The SOUTH STREET REPAVING AND IMPROVEMENTS project includes curb and sidewalk replacement along South Street (US-68) between Main Street and Locust Street. Resurface South Street between Main Street and Columbus Street. Install storm sewer between alleyway north of Locust Street and Columbus Street along South Street.
ENGINEER'S ESTIMATE: $349,663.44 -Base, $30,756.96- Alternate
| 09/27/2024 04:00 PM UTC |
2024-002 Lime Sludge Removal
Project: REMOVAL AND APPLICATION TO FARMLAND OF SLUDGE FROM THE WILMINGTON WATER PLANT LIME STORAGE FACILITY (LAGOON #2) 2024
Contract ID: 2024-002
Location: Water Treatment Plant, 1142 Prairie Avenue
MANDATORY Pre-Bid Meeting 12:00 Noon August 20, 2024 at project site.
Project Deadline: December 31, 2024
| 08/23/2024 04:00 PM UTC |
2024-001 East Main Street Storm Sewer Replacement
Project: East Main Street Storm Sewer Replacement
Contract ID: 2024-001
Planning Engineer: Paul Goodhue, P.E., PTOE
Design Engineer: Fishbeck
Location: Intersection of E Main St and Grant St Wilmington OH
Project Deadline: July 31, 2024
Engineer's Estimate: $311,500.00
Overview: The project includes replacement and reconstruction of storm sewer pipe and catch basins at the intersection of East Main Street and Grant Street in Wilmington, Ohio. Two curb ramps will be replaced with the project and reconstructed to meet current ADA requirements. Portions of sidewalk may need to be rebuilt to ensure ADA requirements are met.
| 02/28/2024 05:00 PM UTC |
2023-008 Thorne Avenue Drainage Improvements
Project: Thorne Avenue Drainage Improvements
Contract ID: 2023-008
Planning Engineer: Paul Goodhue, P.E., PTOE
Design Engineer: LJB Inc.
Location: Thorne Avenue
Project Deadline: June 30, 2024
Engineer's Estimate: $167,982.12
Overview:
The proposed drainage project constructs storm sewer improvements on private properties west of Thorne Avenue south of Wilmington High School. The work includes excavation, trenching, installation of storm sewer pipes, inlets, underdrains and manholes.
The Contractor shall be aware that this work will be primarily performed on private properties. The City is in the process of securing work agreements with the property owners. The Contractor is required to coordinate with Wilmington High School administration and may need to adjust the work schedule accordingly. Construction activities during school arrival and dismissal periods are prohibited.
| 01/10/2024 05:00 PM UTC |
2023-003 CLI Wilmington Crossings FY23
PROJECT: CLI WILMINGTON CROSSING FY23
CONTRACT ID: 2023-003
ODOT PID: 117146
PLANNING ENGINEER: Goodhue Consulting, LLC
DESIGN ENGINEER: LJB
LOCATION: City of Wilmington - Various Locations
PROJECT DEADLINE: June 30, 2024
OPTIONAL PRE-BID MEETING: NONE
OVERVIEW: The CLI WILMINGTON CROSSINGS FY23 project is comprised of construction of seven pedestrian crosswalk improvements throughout the City of Wilmington. The project includes improved signage and markings, ADA-compliant upgrades, sidewalks, and traffic calming measures. The locations are: Truesdell Street at Holmes Elementary School and Piedmont Street, Locust Street mid-block crossing at City Municipal Building, N. South Street Mid-block crossing north of Birdsall Street, Nelson Avenue at Luther E Warren Peace Path Trail, S. South Street mid-block crossing south of Sugartree Street, Mulberry Street at Luther E. Warren Peace Path Trail, and Thorne Avenue midblock crossing at Wilmington High School Athletic Complex.