City of Sidney
Engineering Department 201 W. Poplar Street, Sidney, OH 45365
(937) 498-8142
The City of Sidney is a full-service community located along the Great Miami River in Shelby County, Ohio.
Engineering Department 201 W. Poplar Street, Sidney, OH 45365
(937) 498-8142
The City of Sidney is a full-service community located along the Great Miami River in Shelby County, Ohio.
Name * | Description | |
---|---|---|
Number | Deadline |
---|---|
Number | Deadline |
---|---|
22-09
22-09 Marilyn Drive & Ann Place Sanitary Sewer Replacement
The project includes the replacement of existing sanitary sewer and laterals; reconstruction of curb and roadway; and associated storm sewer work.
Estimate: $612,019
| 03/17/2022 03:30 PM UTC |
22-04
22-04 WATER WELL #9 REHABILITATION
The project includes the furnishing of all labor, materials, transportation, tools, supplies, equipment, and appurtenances necessary for the repair and redevelopment of the City's #9 Water Well.
A non-mandatory Pre-Bid Meeting will be held at 9:30 a.m. on Wednesday, February 23, 2022 at the Water Treatment Plant, 880 E. Court Street, Sidney, Ohio. Please RSVP to sepley@sidneyoh.com if you plan to attend the prebid meeting.
Construction Estimate: $60,000
| 03/10/2022 09:00 PM UTC |
22-06
22-06 2022 Sidewalk Program
The project will consist of the removal and replacement of 4" and 6" concrete sidewalk and drive approaches, replacement of curb, and seeding & mulching.
Construction Estimate: $209,788
| 03/10/2022 04:30 PM UTC |
22-07
22-07 WWTP Biosolids Disposal
Description of Job: The project will include removal and disposal of 500-700 dry tons of Wastewater Treatment Plant biosolids per each year of the Contract.
Budget Amount year 2022 $48,000
| 03/10/2022 04:00 PM UTC |
22-05 Taxiway A Rehabilitation & Lighting Improvement
22-05 Taxiway A Rehabilitation & Lighting Improvement
The project includes milling, asphalt crack repair, asphalt pavement, pavement markings, and airfield lighting.
Engineer's Estimate: $401,660
| 03/03/2022 04:00 PM UTC |
22-03
22-03 2022 STREET RESURFACING
The project includes planning of asphalt, placement of asphalt surface course, asphalt concrete surface course, thermoplastic paint markings, and traffic loop.
Construction Estimate: $1,450,327
ADDENDUM #1 Construction Estimate: $1,718,967
ADDENDUM #2 Construction Estimate: $1,724,836
ADDENDUM #3 Construction Estimate: No change
| 02/03/2022 09:00 PM UTC |
22-02
22-02 Lime Sludge Service Lagoon Cleaning
Description of Job: The project will include removal and disposal of lime softened sludge from the Water Treatment Plant storage lagoon to an approved agricultural site for land application. The estimated dry ton amounts will be based on the City’s yearly budgeted amount.
Budget Amount per year $185,000
| 02/03/2022 08:00 PM UTC |
22-01
22-01
2022 CURB & GUTTER REPLACEMENT
The project consists of the removal & replacement of curb & gutter and curb ramps with truncated domes and also includes the reconnection of drain tiles and site restoration.
Construction Estimate: $475,637
| 02/03/2022 04:30 PM UTC |
21-16
21-16
Linden/Forest Storm Sewer Improvements
The project includes the replacement of storm sewer outlet at the east end of Forest Street from the last existing storm manhole to where the storm sewer outlets within the CSX Railroad right-of-way.
Construction Estimate is $47,434
| 12/16/2021 09:00 PM UTC |
21-15
21-15
SHE-SR 47-13.97
SR 47 SAFETY IMPROVEMENTS IV (4TH TO I-75)
PID 112179
DBE GOAL 6%:
The 0.58 mile long project on SR 47 (Michigan St.) from the SB Interstate 75 ramp east to Fourth Ave. will consist of the following improvements: enhanced crosswalk visibility and signing; addition of countdown pedestrian signals; continuation of a 10 foot wide shared use path from Fourth Ave. to the SB Interstate ramp; removal of 3 drives on the south side of SR 47 near Fifth Avenue; construction of a concrete median at Fifth Ave. to prevent left turns exiting Fifth Avenue; reconstruction of a commercial drive approach on the south side of the Sixth Ave. intersection and installation of a mast arm traffic signal with backing plates at the same intersection; widen the south side of SR 47 at Sixth Ave and add a U-turn lane for WB traffic to return east; Removal and replacement of existing guardrail from Fifth Ave. to Fourth Ave. with concrete median; reconstruct pavement on south lanes of SR 47 at Fourth Ave. and install a concrete left turn lane; mill and resurface SR 47 along the entire length of the project and upgrade signs and pavement markings.
Construction Estimate with Base Bid and either Alternate 1 or Alternate 2 is $2,320,999.
| 12/16/2021 04:30 PM UTC |