St. Tammany Parish Government
PO Box 628, Covington, LA 70434-0628
(985) 898-2520
PO Box 628, Covington, LA 70434-0628
(985) 898-2520
| Name * | Description | |
|---|---|---|
| Number | Deadline |
|---|---|
|
26-13-2
Justice Center Boilers--------------------------Base Bid to include the removal of (2) existing hot water heating boilers with (1) new boiler to be replaced in a configuration similar to existing. Piping for the second boiler shall be stubbed out and capped for future replacement. A rental boiler shall be included to maintain building heating during the project. A new opening and roll door in the boiler room wall to be installed to accommodate boiler removal and installation as well as future service. The door to the loading dock area will be replaced with a pair of 3'-0" x 8'-0" hollow metal doors and hardware to accommodate boiler replacement.
| 04/08/2026 07:00 PM UTC |
|
26-16-2
Rosedown Way Drainage Phase 2--------------
The Contractor shall provide all labor, equipment, tools, testing, and materials
necessary to complete drainage improvements in accordance with the construction
plans and specifications for the Rosedown Subdivision, located in Mandeville,
Louisiana, 70471. The work includes replacement of existing drainage
infrastructure along Camden Court, construction of a new concrete-lined channel
to Lake Vista Drive, replacement of culverts under Lake Vista Drive, and all
incidental work, such as replacement of concrete street panels, sidewalks, and
driveways, utility relocations, installation of sewer and water conflict boxes, and
placement of rip rap at the outfall.
| 04/14/2026 07:00 PM UTC |
|
26-18-2
2026 District 7 Road Improvements-------------
The Contractor shall provide all adequate and competent labor, equipment, tools, testing, and materials necessary to improve roadways by milling and overlaying road surfaces along various District 7 Parish roads.
| 04/14/2026 07:00 PM UTC |
|
26-19-2
2026 District 2, 3 Road Improvements----------
The Contractor shall provide all adequate and competent labor, equipment, tools, testing, and materials necessary to improve roadways by milling and overlaying, patching, and reconstructing road surfaces as specified along various District 2 and District 3 Parish roads.
| 04/14/2026 07:00 PM UTC |
|
26-22-2
Emergency Fuel Services--------------------------
The St. Tammany Parish Government (Parish) is seeking a qualified vendor to establish a standby contract for emergency fuel supply and distribution services to be utilized during declared emergency events.
| 04/21/2026 07:00 PM UTC |
|
26-21-2
2026 District 6, 8, 9 Road Improvements------
The Contractor must provide all adequate and competent labor, equipment, tools,
testing, and materials necessary to improve roadways by milling and/or overlaying
road surfaces as specified along various District 6, 8, and 9 Parish roads.
| 04/28/2026 07:00 PM UTC |
|
26-20-2
Goldenwood Drive Drainage--------------------------------------The Contractor must provide all adequate and competent labor, equipment, tools,testing, and materials necessary to improve drainage by cleaning and installing CIPP liner in the drain pipe as specified along Goldenwood Dr (R08M061), located in Slidell, LA.
| 05/05/2026 07:00 PM UTC |
| Number | Deadline |
|---|---|
|
25-22-1
Lenwood Dr Pond & Lowe Pond Fence Repairs----The Contractor must provide all adequate and competent labor, equipment, tools, testing, and materials necessary to repair existing fence and install new fence and gates, as specified along Lenwood Dr (P08IW01132); and Lowe Pond (P08AW02007) located in Slidell, Louisiana.
| 04/30/2025 07:00 PM UTC |
|
25-24-1
Chamale Dr. & Weil Wood Dr.------ The parish requests a contractor to improve roadways by patching, installing asphalt speed
tables, improving turn radius, and removing/replacing sidewalk as specified.
| 04/22/2025 07:00 PM UTC |
|
25-21-1
Woodridge Blvd Drainage ------------The Parish requests a contractor to improve drainage by installing catch basins into sub-surface located on Woodridge Blvd (R04C004); in Mandeville, Louisiana.
| 04/02/2025 07:00 PM UTC |
|
25-8-2
Berry Todd Rd & N Dixie Ranch Rd----The work specified in this project will require the contractor to provide labor, equipment, and materials necessary to improve the roadway surfaces by milling and overlaying approximately 21,500 total feet of asphaltic concrete and installing roadway striping, as specified along Berry Todd Rd (R07C002) Section 19/43/39/29/28, Township 8S, Range 13E, and N Dixie Ranch Rd (R07B004) Section 16-17, Township 8S, Range 13E.
The Parish reserves the right to add, remove or otherwise modify the above, as
determined necessary by the Parish and as allowed by law.
The time period for completion of work is forty-five (45) days from issuance of
Notice to Proceed by the Parish.
| 04/01/2025 07:00 PM UTC |
|
25-9-2
2025 District Panel Replacements---------------------------The Contractor must provide all adequate and competent labor, equipment, tools, testing, and materials necessary to improve roadways by removing/replacing and/or repairing concrete panels and concrete rollover/barrier curbs as specified along Maison Dr (R01K015) Covington ; Bluefield Dr (R08I061)Slidell ; Kelly Dr (R08I005) Slidell ; Kris Dr (R08I006) Slidell ; Northwood Dr (R08I030) Slidell ; Timbers Dr (R08I043) Slidell ; Autumn Wind Ln (R04F063) Mandeville ; Brandon Dr (R08P030) Slidell ; West End Blvd (R09J110) Slidell.
| 04/01/2025 07:00 PM UTC |
|
25-18-1
Sycamore Dr Turn Radius----The parish requests a contractor to improve the turning radius at the first part of the s-curve by installing subsurface drainage, catch basins, patching and shoulder material as specified
| 03/13/2025 07:00 PM UTC |
|
25-19-1
Huntwyck Village Sidewalks------The Parish requests a contractor to improve sidewalks at various locations as specified along Drury Ln (R09G037) Slidell; Holmes Dr (R09G040) Slidell; Portsmouth Dr (R09G039) Slidell; Queen Anne Dr (R09G038) Slidell; Raleigh Dr (R09G036) Slidell; Westminster Dr (R09G033) Slidell ; Louisiana.
| 03/13/2025 07:00 PM UTC |
|
25-20-1
7th St. Road Improvement-------------------------------The Parish requests a contractor to improve road surfaces by patching and overlay on 7th St., Mandeville, LA.,
| 03/13/2025 07:00 PM UTC |
|
25-14-1
Adele Ln Sinkhole Repairs -----------The Parish requests a contractor to improve drainage by re-grouting catch basin, wrap pipe joint, remove/replace concrete driveway apron located on Adele Ln (R09A028); in Slidell, Louisiana.
| 03/12/2025 07:00 PM UTC |
|
25-10-2
Excavator-----------------------The Parish extends this MATERIAL ONLY bid request to procure an Excavator. This equipment shall be a new piece of equipment. The Excavator will be procured for the Public Works Department.
| 03/12/2025 07:00 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.