City of Lake Charles
326 Pujo Street, Lake Charles, LA 70601
(337) 491-1263
326 Pujo Street, Lake Charles, LA 70601
(337) 491-1263
| Name * | Description | |
|---|---|---|
| Number | Deadline |
|---|---|
|
CP3427
CITY OF LAKE CHARLES, LOUISIANA
WASTEWATER TREATMENT PLANT B/C
SLUDGE PROCESSING IMPROVEMENTS
CAPITAL PROJECT NUMBER CP3427
I. Scope of Services:
Contractor shall complete the Work as specified and indicated in the Contract Documents for Wastewater Treatment Plant B/C – Sludge Processing Improvements (Capital Project Number CP3427). This Work includes, but is not limited to, the following:
• Removal and Replacement of Pressurized Air Headers/Diffusers within Digestors.
• Installation of Access Hardware for Operation/Maintenance of Digestors.
• Construction of New Blower Building for Process Equipment.
• Removal and Replacement of Air Blowers and Header Piping for Aerated Digestion.
• Construction of New Motor Control Center.
• Reconstruction of Existing Sludge Pump Station.
• Construction of New Sludge Processing Building.
• Installation of Screw Presses for Solids Processing.
• Installation of Dewatering Polymer Feed System.
• Installation of Conveyance System for Solids Handling/Disposal.
• Interconnections to Owner’s SCADA for Control/Monitoring.
• Miscellaneous Civil, Mechanical, and Electrical Work as Required to Complete the Work.
| 12/16/2025 08:45 PM UTC |
|
Project No. 2025-748 Capital Project No. 3224
City of Lake Charles, Louisiana
Muirfield Drive Drainage-Phase II
Project No. 2025-748
Capital Project No. 3224
The general scope of work for Muirfield Drive Drainage Phase II consists of the installation of approximately 1400 linear feet of 36” diameter storm drainage pipe to augment the existing drainage system. This pipe installation begins on the west side of Lot 19 of Turnberry Row subdivision and continues to the west line and into Lot 5 of the Muirfield Village Phase One subdivision. This additional drainage system will be installed along and within the limits of the Lake Charles Country Club Golf Course boundary.
| 01/06/2026 08:45 PM UTC |
|
Project No. 2023-726 Capital Project No. 3019
Project No. 2023-726
Capital Project No. 3019
Sale Road Bridge Repair
City of Lake Charles, LA
The general scope of work for this project is the repair of the Sale Road bridge over Lateral L-2A of Contraband Bayou. This bridge exhibited various defects shortly after it was constructed in 2014. These defects included road pavement settlement, broken tie-rods, drainage pipe/box failures, etc. This project’s repair scope includes:
• Construction of a new concrete deadman tie-rod anchor assembly to restore support to the sheet pile wall;
• Replace failed drainage concrete pipe and boxes;
• Removal and replacement of reinforced concrete pavement;
• The associated traffic management, including detour signage.
| 01/06/2026 08:45 PM UTC |
| Number | Deadline |
|---|---|
|
Capital Project Number CP3353
CITY OF LAKE CHARLES, LOUISIANA
CENTER EAST WATER TREATMENT PLANT
PRESSURE FILTER REPLACEMENT
CAPITAL PROJECT NUMBER CP3353
I. Scope of Services:
Contractor shall complete all Work as specified or indicated in the Contract Documents for Center East Water Treatment Plant – Pressure Filter Replacement project. The Work includes, but is not limited to, the following:
• Demolition and Replacement of Existing Pressure Filter (Center East WTP).
• Removal and Replacement of Potassium Permanganate Feed System (Center East WTP).
• Removal and Replacement of Media and Internals within Existing Filter (Chennault WTP).
• Furnish and Install Automated Flow Modulation for Backwash Control (Chennault WTP).
| 05/30/2023 07:45 PM UTC |
|
Project No. 2022-722 Capital Project No. 3428
Project No. 2022-722
Capital Project No. 3428
Various Citywide Drainage & Ancillary Infrastructure Improvements
Phase 1
City of Lake Charles, LA
The general scope of work for this project includes the drainage and other infrastructure improvements/repairs at the following locations:
1. Opal Drive & Yorkshire Drive – The rehab of existing settled drainage box and pipe along with the associated pavement and driveway work.
2. W. Prien Lake Road near Heard Road – The filling/piping in of a portion of the roadside ditch to protect against further erosion.
3. 2500 Block of Fitzenreiter Road – Rehab of existing compromised drainage box and pipe.
4. Doolan Lane – The filling/piping in of a portion of the Doolan Lane’s roadside ditch from 18th Street South approximately 75 feet. This is being done to protect against further erosion.
5. Bancroft Street – Drainage improvements at the West end of Bancroft Street.
| 05/16/2023 07:45 PM UTC |
|
CP 3384
City of Lake Charles, Louisiana
Power Centre Parkway Sidewalks
CP 3384
I. Scope of Work:
The scope of work for this project is to install sidewalks on the South side of Power Centre Parkway from 5th Avenue to Amoco Rd. East of Hwy. 14. The sidewalks will tie into the existing sidewalks from the Cottages at Power Centre on the southwest side of the 5th Avenue and Power Centre Parkway intersection, crosswalk across 5th Avenue, connect to the existing 5th Avenue sidewalks along the east side, and traverse along the south side of 5th avenue approximately 0.50 miles to Highway 14. This will be followed by a crosswalk with pedestrian signal across Highway 14, and approximately 0.18 miles of new sidewalk along the south side of Power Centre Parkway, connecting to the existing sidewalk near the southwest corner of Amoco Dr. intersection in front of the Lake Charles Charter Academy. The Hwy. 14 crossing requires signal work to modify the traffic pattern to include the pedestrian sequence. The engineering and design has already been included in the project plans and specs. Each of the intersections and driveways, etc. will required removal of existing curb to modify for ADA accessible ramps. See plan sheets and specs for more details and locations.
| 05/16/2023 07:45 PM UTC |
|
Project No. 2022-724 Capital Project No. 3003
PROJECT NO. 2022-724
CAPITAL PROJECT NO. 3003
NORTH BEACH RECREATIONAL PIER
CITY OF LAKE CHARLES, LA
The general scope of work for this project is the installation of recreational pier and floating dock along the north beach of Lake Charles. This pier and floating dock will total approximately 130 long. It will consist of a timber pile supported fixed pier with composite lumber decking and framing. A metal gangway will connect this fixed pier to the floating dock.
| 04/04/2023 07:45 PM UTC |
|
RFP #2023-22, File ID #718-22
PROFESSIONAL SERVICES – PROGRAM MANAGER FOR CITY OF LAKE CHARLES COMMUNITY DEVELOPMENT BLOCK GRANT-DISASTER RECOVERY (CDBG-DR) ALLOCATION FROM THE STATE OF LOUISIANA, OFFICE OF COMMUNITY DEVELOPMENT (OCD)
| 04/04/2023 07:45 PM UTC |
|
CP3406
City of Lake Charles, Louisiana
Corbina Road Water Main Extension – James Court to W. Prien Lake Road
CP3406
SCOPE OF WORK:
Project scope consists of the installation of a proposed watermain along Corbina Road in Lake Charles, LA. The project scope shall include, but it not limited to, the installation of a 16” diameter watermain, gate valves, fire hydrants, ductile iron fittings, material, equipment and labor. The installation of the proposed watermain by horizontal and directional drilling will be required for approximately 1,100 linear feet.
PROJECT LIMITS:
The project limits are along the eastern side of Corbina Road extending from James Court to E. Prien Lake Road.
| 04/04/2023 07:45 PM UTC |
|
Capital Project Number CP3251
City of Lake Charles
University Area Blue Sub-Basin Sewer Rehabilitation
Capital Project Number CP3251
I. Background:
The University area is one of the oldest areas in the City of Lake Charles. Wastewater flow studies have indicated excessive inflow and infiltration during rain events, causing peak flows up to 14 times the average daily wastewater rate.
II. Scope of Services:
Based on review of the CCTV data of the sewer line cleaning and CCTV project within the University area, the assessed pipelines have been designated as critically deficient and priority one deficient. Following review of the assessment the following scope of work has been developed.
A. There is approximately 3,215 LF of 8” sewer pipe that has been identified as critical deficiencies and an additional 7,948 LF of 8” sewer pipe that has been identified as priority one deficiencies that will be rehabilitated as part of the base bid of this project.
B. Manchac Consulting Group, Inc. will analyze the CCTV data provided, and rehabilitation methods will be refined upon review of the CCTV data during final design. Rehabilitation methods include pipe bursting, point repairs, cured-in-place lining, and manhole lining.
| 04/04/2023 07:45 PM UTC |
|
Project No. 2022-720 Capital Project No. PR0002
Project No. 2022-720
Capital Project No. PR0002
North Beach Improvements
City of Lake Charles, LA
This project provides for an improved parking area along the South l-10 service road that will serve a proposed future commercial development. This development is located west of the existing Wildlife and Fisheries building and East of the current sand beach.
Additional items anticipated with this project include the following:
• Re-configure the existing north beach parking lot exit. This exit will be shifted westerly to comply with LA DOTD separation requirements.
• Provide sewer and water service taps for future commercial development prior to hard surfacing the parking area.
| 03/14/2023 07:45 PM UTC |
|
HL-14
City of Lake Charles, Louisiana
Lake Charles Civic Center Hurricane Laura Restoration – Exterior Repairs
HL-14
1. Replace damaged and missing stucco wall panel system on South Wall. Restore to pre- disaster conditions. Color of finish on wall panels shall be selected by Owner. All existing similar panels on South wall will be patched and recoated with similar finish. Seal all joints. Approx 1300 SF
2. Replace existing temporary stud wall in area of missing wall panels at upper south wall and replace with new structural steel studs, insulation, and fireproofing.
3. Repair and replace 2’-3’ tall aggregate panel where missing at top of South Wall. Match existing if possible. Seal and paint to match existing aggregate fascia panel, approx. 100 LF. Provide structural steel stud framing. Seal all joints.
4. Repair damaged balcony walkway and railing at South elevation. Install new structural steel connection to support existing beams. (2 connectors)
5. Replace plaster soffit where removed at third level on the East side and where damaged under upper-level canopy at North wall. Replace plaster soffits at south end under failed walkway canopy where removed to repair structure.
6. Repair any damaged aggregate wall panels where holes occur. Approx. includes 6 locations
7. Miscellaneous repairs to aluminum storefront entrances.
8. Clean all surfaces and waterproof all exterior surfaces.
| 03/14/2023 07:45 PM UTC |
|
Capital Project Number CP3246
City of Lake Charles
Wastewater System Improvements
Salene Road, Lawrence Lane, and A. Miller Road
Capital Project Number CP3246
I. Scope of Services:
A. There are currently no City wastewater services available on Salene Road, Lawrence Lane, and A. Miller Road. It is the City’s desire to provide sewer service for the residents on these streets. Due to the higher capital costs associated with conventional gravity collection systems, it is the intent of the City to provide a low pressure sewer collection system for this area.
B. Three forcemains will be designed as part of this project to allow for each home to connect to one of the forcemains via low pressure wastewater pump. One forcemain will be located on each street and will discharge into the existing manholes located at the end of each street near Big Lake Road. The wastewater pump located at each home and a small diameter forcemain from each home that would connect to the City’s new forcemains will not be designed as part of this project.
C. The Work includes, but is not necessarily limited to, the following:
• Directional drill of 2,264 linear feet of 2” HDPE and 766 linear feet of 3” HDPE sewer forcemain.
• Directional drill 800 linear feet of 1.25” HDPE and open cut 140 LF of 1.25” HDPE lateral pipe.
• Install 50 lateral kits and service connections to new sewer forcemain.
• Coating approximately 27 vertical feet of existing manholes.
• Procurement and Furnishing of 15 E-One Grinder Stations to COLC Wastewater Department
| 02/28/2023 08:45 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.