CITY OF LAKE CHARLES, LOUISIANA
WASTEWATER TREATMENT PLANT B/C
SLUDGE PROCESSING IMPROVEMENTS
CAPITAL PROJECT NUMBER CP3427
I. Scope of Services:
Contractor shall complete the Work as specified and indicated in the Contract Documents for Wastewater Treatment Plant B/C – Sludge Processing Improvements (Capital Project Number CP3427). This Work includes, but is not limited to, the following:
• Removal and Replacement of Pressurized Air Headers/Diffusers within Digestors.
• Installation of Access Hardware for Operation/Maintenance of Digestors.
• Construction of New Blower Building for Process Equipment.
• Removal and Replacement of Air Blowers and Header Piping for Aerated Digestion.
• Construction of New Motor Control Center.
• Reconstruction of Existing Sludge Pump Station.
• Construction of New Sludge Processing Building.
• Installation of Screw Presses for Solids Processing.
• Installation of Dewatering Polymer Feed System.
• Installation of Conveyance System for Solids Handling/Disposal.
• Interconnections to Owner’s SCADA for Control/Monitoring.
• Miscellaneous Civil, Mechanical, and Electrical Work as Required to Complete the Work.
| 12/16/2025 08:45 PM UTC |
|
Project No. 2025-748 Capital Project No. 3224
City of Lake Charles, Louisiana
Muirfield Drive Drainage-Phase II
Project No. 2025-748
Capital Project No. 3224
The general scope of work for Muirfield Drive Drainage Phase II consists of the installation of approximately 1400 linear feet of 36” diameter storm drainage pipe to augment the existing drainage system. This pipe installation begins on the west side of Lot 19 of Turnberry Row subdivision and continues to the west line and into Lot 5 of the Muirfield Village Phase One subdivision. This additional drainage system will be installed along and within the limits of the Lake Charles Country Club Golf Course boundary.
| 12/16/2025 08:45 PM UTC |
|
Project No. 2023-726 Capital Project No. 3019
Project No. 2023-726
Capital Project No. 3019
Sale Road Bridge Repair
City of Lake Charles, LA
The general scope of work for this project is the repair of the Sale Road bridge over Lateral L-2A of Contraband Bayou. This bridge exhibited various defects shortly after it was constructed in 2014. These defects included road pavement settlement, broken tie-rods, drainage pipe/box failures, etc. This project’s repair scope includes:
• Construction of a new concrete deadman tie-rod anchor assembly to restore support to the sheet pile wall;
• Replace failed drainage concrete pipe and boxes;
• Removal and replacement of reinforced concrete pavement;
• The associated traffic management, including detour signage.
| 12/16/2025 08:45 PM UTC |
| Number | Deadline |
|---|---|
|
Project No. 2016-658, Capital Project No. 3288
Project No. 2016-658
Capital Project No. 3288
48” CIPP Lining from The Holly Hill Road/Prien Lake Road Roundabout
North to the Contraband Bayou Lift Station
City of Lake Charles, LA ~
The general scope of work for Project No. 2016-658, Capital Project No. 3288, includes the rehabilitation of approximately 2600 feet of 48 inch sewer main by cured-in-place (CIPP) lining from the Holly Hill Road/Prien Lake Road Roundabout North to the Contraband Bayou Lift Station. A system for bypass pumping to manage sewage flow must be furnished and maintained. Manhole tops will require removal and re construction to facilitate liner installation. Concrete and/or brick manholes will also be rehabilitated with new interior liners.
| 02/20/2018 08:45 PM UTC |
|
Capital Project Number CP3302
Capital Project Number CP3302
Southwest Water Treatment Plant
Horizontal Pressure Filter Rehabilitation
City of Lake Charles, LA ~
I. Scope of Services:
The City of Lake Charles desires to rehabilitate the six (6) existing horizontal pressure filters at the Southwest Water Treatment Plant. This Work will include but is not limited to the following:
1. Removal and replacement of the Filter Media within Filters #1 – 6
a. Estimated Total Volume Needed: 4,320 ft.3
b. 24” Layer of Manganese Greensand & 12” Layer of Anthracite
2. Removal and replacement of the Existing Gravel Bed and Retaining Screen
3. Removal and replacement of the Existing Underdrain Valves
4. Removal and replacement of additional Filter Internals as Required
5. Removal and replacement of the existing air scour piping and discharge nozzles.
6. Removal and replacement of the existing backwash water flow meter.
| 02/20/2018 08:45 PM UTC |
|
Project No. 2016-650, Capital Project No. 3268
Project No. 2016-650
Capital Project No. CP3268
Nelson Road Sewer Force Main Upgrade
Country Club Road to Linden Lane
City of Lake Charles, LA ~
This scope of work for Project No. 2016-650, Nelson Road Sewer Force Main Upgrade – Country Club Road to Linden Lane, includes the installation of a new 10 inch diameter force main from the intersection of Nelson Road and Country Club Road South to tie into an existing 10 inch diameter force main North of Linden Lane. This new force main will service the existing Pecan Acres sewer lift station and will include a connection for the option of receiving flow from the Nelson Pointe Apartments sewer lift station.
| 02/06/2018 08:45 PM UTC |
|
Capital Project No. CP3128
WWTP B/C Expansion and Rehabilitation Project
Phase I Demolition
Capital Project Number CP3128
City of Lake Charles, LA ~
I. Scope of Services:
A. A new WWTP B/C facility is currently under construction for The City of Lake Charles. Decommissioning of the existing WWTP B/C has been divided into two phases.
B. This scope of work covers Phase I of the demolition. The Work includes, but is not necessarily limited to, the following:
1. Removal and disposal of mechanical and electrical equipment from existing tankage at existing WWTPs B and C.
2. Demolition and filling of existing tankage at existing WWTPs B and C.
3. Installation of approximately 250 linear feet of 8-inch PVC, 20 linear feet of 24-inch ductile iron pipe, 90 linear feet of 30-inch HDPE, 372 linear feet of 48-inch ductile iron pipe, one new reinforced cast in place concrete collection box, and one 8-ft diameter FRP manhole.
4. Coating of two existing manholes and one new reinforced cast in place concrete collection box.
| 01/16/2018 08:45 PM UTC |
|
Capital Project No. CP3264
Capital Project No. CP3264
Interstate Corridor Beautification Project Phase I
REBID
City of Lake Charles, LA ~
NORTH I-10 EXIT RAMP 30 B AND SERVICE ROAD- LaDOTD PERMIT 153562
SOUTH I-10 SERVICE ROAD LaDOTD PERMIT 153565
COVE LANE AND ROUNDABOUT- LaDOTD PERMIT 153586
SCOPE OF WORK
The general scope of work for Project Interstate Corridor Beautification Phase I, Capital Project No. 3264, includes the following.
North I-10 Exit Ramp 30 B and Service Road - Installation of trees, palms, and shrubs.
South I-10 Service Road - Installation of trees, palms, and shrubs.
Cove Lane and Roundabout - installation of trees, palms, shrubs, and installation within the roundabout borrow fill material, concrete curbing, aluminum edging, and decorative stone with binding solution.
| 01/16/2018 08:45 PM UTC |
|
Project No. CP3264 Interstate Corridor Beautification Phase I (REBID)
Capital Project No. CP3264
Interstate Corridor Beautification Project Phase I
REBID
City of Lake Charles, LA ~
NORTH I-10 EXIT RAMP 30 B AND SERVICE ROAD- LaDOTD PERMIT 153562
SOUTH I-10 SERVICE ROAD LaDOTD PERMIT 153565
COVE LANE AND ROUNDABOUT- LaDOTD PERMIT 153586
SCOPE OF WORK
The general scope of work for Project Interstate Corridor Beautification Phase I, Capital Project No. 3264, includes the following.
North I-10 Exit Ramp 30 B and Service Road - Installation of trees, palms, and shrubs.
South I-10 Service Road - Installation of trees, palms, and shrubs.
Cove Lane and Roundabout - installation of trees, palms, shrubs, and installation within the roundabout borrow fill material, concrete curbing, aluminum edging, and decorative stone with binding solution.
| 01/16/2018 08:45 AM UTC |
|
Capital Project Number OP 0601
Capital Project Number OP 0601
Chennault Water Treatment Plant
400,000 Gallon Elevated Water Storage Tank Rehabilitation
City of Lake Charles, LA ~
I. Scope of Services:
A. The City of Lake Charles Water Division currently owns and operates the 400,000 Gallon Elevated Storage Tank at the Chennault Water Treatment Plant. Rehabilitation of the existing tank in general includes:
a. Drainage improvements around the tank
b. Erection and maintenance of a temporary containment system to contain sand blasting and paint debris from falling on adjacent properties and vehicles.
c. Light sand blasting of the tank exterior and appurtenances and applying a three coat exterior coating system to the entire tank exterior.
d. Sandblasting interior tank walls and appurtenances and applying 3 coat interior coating system to these surfaces.
e. Perform the necessary adjustments to windages/sway rods to return the tank to its original erect, design conformance.
f. Furnish and install repairs and improvements to the interior roof, vent, roof ladder, etc.
g. Remove and dispose of existing overflow piping within tank riser and buried vault. Install new, exterior overflow piping to discharge into a closed drainage
system to be routed to the adjacent ditch.
| 01/02/2018 08:45 PM UTC |
|
Capital Project No. CP3273, LEI Project No. 17-011
Capital Project No. CP3273
LEI Project No. 17-011
2017 Asphalt Overlays
City of Lake Charles, LA ~
SCOPE OF WORK
The intent of this Contract is to provide for construction and completion, in every detail, of the Work described. It is further intended that the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies required to complete the Work in accordance with the plans, specifications, and terms of the Contract.
The project consists of pavement patching, degrassing edge of road and grading shoulders, adjusting sanitary sewer manholes to grade, adjusting storm drain catch basins to grade, cold planing asphaltic concrete pavement, asphaltic concrete surface course, pavement markings, asphaltic concrete ramps at paved driveways, aggregate surface course on aggregate driveways, topsoil shoulder material, and hydro-seeding for the following streets at various locations in the City of Lake Charles:
1. Edgewood Lane (West Prien Lake Road to Magnolia Lane)
2. Mount Talbot Street (Fruge Street to McNabb Street)
3. Timberline Drive (Shasta Street to Dead End)
4. Cappy Drive (Nelson Road to Sale Road)
5. Charles Drive (Lela Drive to Nelson Road)
6. Lela Drive (Sale Road to Cappy Drive)
7. Junior Street (Napp Street to Theriot Street)
8. Tuten Drive (Cappy Drive to Charles Street)
9. Nicholas Street (Nelson Road to Dead End)
10. Melvin Lane (Alma Lane to Nelson Road)
11. Ponderosa Drive (Lisle Peters Road to Dead End)
12. Opelousas Street (North Louisiana Avenue to Enterprise Boulevard))
13. Walker Street (Poe Street to Medora Street)
14. Highway Street (Highway 171 to North Grace Street)
15. North Grace Street (Medora Street to Dead End)
16. Street Removed from Project
17. North Louisiana Avenue (Opelousas Street to Bauer Street)
18. Fournet Street (North Louisiana Avenue to Enterprise Boulevard)
19. Poe Street (Highway 171 to Walker Street)
20. Magnolia Lane (West Prien Lake Road to Edgewood Lane)
| 12/19/2017 08:45 PM UTC |
|
Project No. CP3242
Capital Project No. CP3248
WWTP A Basin A-04 Rehabilitation Project
City of Lake Charles, LA ~
I. Scope of Services:
A. The City of Lake Charles WWTP ‘A’ is currently under a Compliance Order (CO) with LDEQ. The approved CO schedule requires the rehabilitation of 13 sub basins in the WWTP ‘A’ Basin. The Sub Basins have been prioritized and ranked in order of severity of condition through wastewater modeling of the system.
B. Based on review of CCTV data of the Sub-Basin, recommendations for repair have been made and a cost estimate has been developed.
C. This scope of work covers the repair of the collection system in the WWTP A Sub Basin A-04. The Work includes, but is not necessarily limited to, the following:
1. Pipe bursting 16,560 linear feet of existing 6” and 8” sewer to new 8”.
2. Open cut and replace 1,716 linear feet of existing 6” and 8” sewer to new 8”.
3. Replacement of approximately 275 active sewer service laterals.
4. Coating approximately 350 vertical feet of existing and new manholes.
| 12/19/2017 08:45 PM UTC |
|
Project No. 2016-656, Capital Project No. 3252
Project No. 2016-656
Capital Project No. 3252
South Roosevelt Drainage Improvements Phase One
City of Lake Charles, LA ~
The general scope of work for Project No. 2016-656 includes installation of reinforced concrete pipe and catch basins for drainage improvements at the intersection of McKinley Street and South Roosevelt Street. The new drainage outfall pipe will discharge South to Lateral L-14 of W-20 Main.
| 11/14/2017 08:45 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.