Iowa State University
700 Wallace Rd Gen Serv/Room 200, Ames, IA 50011-4012
(515) 294-0366
700 Wallace Rd Gen Serv/Room 200, Ames, IA 50011-4012
(515) 294-0366
Name * | Description | |
---|---|---|
Number | Deadline |
---|---|
CP1191717-General Services Building-AHU12-Replacement
This project includes but is not limited to the replacement of Air Handling Unit 12 (AHU12), including associated plumbing, ductwork, electrical service, insulation, and controls. This unit provides heating, cooling, and limited ventilation to several workspaces.
| 12/05/2024 08:01 PM UTC |
CP002466-Utilities-Power Plant-Station Power Improvements-Phase 5
THIS PROJECT WILL REPLACE AND RECONFIGURE THE STATION POWER SYSTEM WITHIN THE UNIVERSITY POWER PLANT. THE STATION POWER SYSTEM CONSISTS OF THE INTERNAL 15,000 AND 5,000 VOLT SWITCHGEAR, INTERNAL SUBSTATIONS, 480 VOLT LOAD CENTERS, MOTOR CONTROL CENTERS, AND ESSENTIAL POWER SYSTEMS. THE PROJECT WILL TAKE PLACE IN MULTIPLE PHASES OVER MULTIPLE YEARS IN ORDER TO MAINTAIN PLANT OPERATIONS.
| 12/19/2024 08:01 PM UTC |
CP1250785-Beyer Hall-Swimming Pool Repairs-Phase 2
This project includes, but is not limited to, repairs to the existing Beyer Hall swimming pool equipment. Work includes capping the surge tank to prevent chloramine gas from entering the equipment room, and the replacement of the above-ground pool piping, circulation and drain pumps, and the sand filtration system.
| 12/19/2024 08:01 PM UTC |
Number | Deadline |
---|---|
CP002505-Sports Performance Center & Jack Trice Stadium Improvements North-Bergstrom Football Complex-Rooms 2050, 2054, and 2056
The project consists of, but is not limited to, interior demolition of existing metal stud walls and finishes. New construction to include new metal stud walls and finishes, ceilings, lighting, mechanical and new corridor carpeting.
| 05/05/2022 07:01 PM UTC |
CP936596-Veterinary Medicine-Rooms 2401, 2402, 2403, and 2404-Remodel
The project consists of, but is not limited to, remodeling existing meeting rooms with new partition walls, carpet, ceiling tiles, windows, and doors. Also replacing light fixtures, receptacles, and furniture.
| 05/03/2022 07:01 PM UTC |
CP002745-Stephens Auditorium-Roof Replacement-Section A
The project consists of, but is not limited to, installing new fully adhered 90 mil EPDM roof membrane and insulation system over the existing roof membrane and insulation. Provide and install new flashings and roof expansion covers.
| 04/28/2022 07:01 PM UTC |
CP002758-Kildee Hall-Roof Replacement-Section A and B
The project consists of, but is not limited to, replacing the roof system with a more substantial replacement, increasing insulation to current energy codes, and adding the appropriate roof safety systems and equipment.
| 04/26/2022 07:01 PM UTC |
CP919196-Fire Service Storage Building-Demolition
The project consists of, but is not limited to, demolition of selected site facilities and other structures and site restoration including grading and seeding.
| 04/14/2022 07:01 PM UTC |
CP898870-Southeast Recreation Complex-Pavilions
The project consists of, but is not limited to, constructing a pavilion style shelter at the Southeast Recreation Complex. The pavilion will consist of a metal roof, concrete slab, metal columns, power, and data. This project will also relocate the weather detection system.
| 03/24/2022 07:01 PM UTC |
CP940361-Johnny Majors Practice Field-Turf Improvements
This project will prepare the northern portion of Johnny Majors Practice Field for a synthetic turf surface to be installed by others. The project consists of, but is not limited to, subdrain, granular subbase, nailer board, laser grading, electrical improvements and associated site upgrades adjacent to the practice field.
| 03/22/2022 07:01 PM UTC |
CP921822-Utilities-Square Lid Vault Top-Replacements
The project consists of, but is not limited to, the replacement of eight (8) existing underground electrical and telecom vault top concrete slabs that have square manhole lids, with new concrete slabs with ISU standard round manhole lids. This project will involve excavating around the central campus electrical/telecom vaults, sidewalk removal and replacement, re-grading around vaults, concrete removal, and new cast-in-place concrete and rebar work.
| 03/03/2022 08:01 PM UTC |
CP923004-Utilities-Pearson Substation-13.8kV Feeder Cable Replacement
The project consists of, but is not limited to, removal and replacement of 13,800V cable in existing conduits between underground vaults and above ground switchgear, cable splices in existing underground vaults, and cable terminations in above ground switchgear. Perform hi-pot cable tests on installed cable, splices, and terminations.
| 02/24/2022 08:01 PM UTC |
CP002466-Utilities-Power Plant-Station Power Improvements-Phase 4
The project consists of, but is not limited to, the replacement of two each 4160-volt Metal clad switchgears, installation of new medium voltage cables, expansion of an existing SCADA control system, installation of 480-volt panels, 120/208-volt panels, 125-volt DC Panels, transfer switches, 480:120/208-volt transformers and associated 600-volt class cables within the Iowa State University Power Plant. Additional work includes the demolition of 2 existing 4160-volt Metal clad switchgears, one 4160-volt metal enclosed switchgear, one 4160-volt Motor Control Center, one 480-volt Motor Control Center and multiple 480-volt and less power panels and associated equipment, raceways and cables. Architectural/Structural work includes, but is not limited to, the construction of two rooms, demolition of two rooms and the infill of a large opening on the first floor of the Power Plant. Mechanical work includes, but is not limited to, the relocation and installation of steam, condensate, chilled water, domestic water, fire protection, and demineralizer piping systems, relocation of steam supplied unit heaters, the replacement of one roof top HVAC unit and the installation of two new air handling units. All work will occur and be scheduled while keeping the Power Plant fully operational.
| 02/08/2022 08:01 PM UTC |