Iowa State University
700 Wallace Rd Gen Serv/Room 200, Ames, IA 50011-4012
(515) 294-0366
700 Wallace Rd Gen Serv/Room 200, Ames, IA 50011-4012
(515) 294-0366
Name * | Description | |
---|---|---|
Number | Deadline |
---|---|
CP1191717-General Services Building-AHU12-Replacement
This project includes but is not limited to the replacement of Air Handling Unit 12 (AHU12), including associated plumbing, ductwork, electrical service, insulation, and controls. This unit provides heating, cooling, and limited ventilation to several workspaces.
| 12/05/2024 08:01 PM UTC |
CP002466-Utilities-Power Plant-Station Power Improvements-Phase 5
THIS PROJECT WILL REPLACE AND RECONFIGURE THE STATION POWER SYSTEM WITHIN THE UNIVERSITY POWER PLANT. THE STATION POWER SYSTEM CONSISTS OF THE INTERNAL 15,000 AND 5,000 VOLT SWITCHGEAR, INTERNAL SUBSTATIONS, 480 VOLT LOAD CENTERS, MOTOR CONTROL CENTERS, AND ESSENTIAL POWER SYSTEMS. THE PROJECT WILL TAKE PLACE IN MULTIPLE PHASES OVER MULTIPLE YEARS IN ORDER TO MAINTAIN PLANT OPERATIONS.
| 12/19/2024 08:01 PM UTC |
CP1250785-Beyer Hall-Swimming Pool Repairs-Phase 2
This project includes, but is not limited to, repairs to the existing Beyer Hall swimming pool equipment. Work includes capping the surge tank to prevent chloramine gas from entering the equipment room, and the replacement of the above-ground pool piping, circulation and drain pumps, and the sand filtration system.
| 12/19/2024 08:01 PM UTC |
Number | Deadline |
---|---|
CP002436 - Friley Residence Hall Window Replacement
The project consists of, but is not limited to the installation of new aluminum windows throughout Friley Hall to replace existing windows removed under separate abatement contract, (exceptions noted in documents). New accessory items to the window installation are included as well as patch, repair and painting of existing wall construction to facilitate installation of new window assemblies. Construction will be completed during multiple phases during summers only – see Construction Progress Schedule and substantial completion dates.
| 01/25/2018 08:01 PM UTC |
CP002409 - Barton-Lyon-Freeman-Roof Replacements
The project consists of roof replacement work at Barton, Freeman and Lyon Residence Halls. Work consists of, but is not limited to, removal of slate roof system, slate dormer sidewall tiles, dispose. Remove metal gutters and downspouts, dispose. Install new metal gutter and downspouts. Install new asphalt shingle roof system over ice and water shield membrane and roofing accessories. Repair and/or replace damaged wood items as indicated in documents.
| 01/23/2018 08:01 PM UTC |
CP002249 - MacKay Hall-Center Wing Window Replacement
The project consists of, but is not limited to, the replacement of 23 window assemblies and 3 door assemblies on the south side, center wing of MacKay Hall. Windows are on the basement, first, and second floors and shall be replaced with metal clad wood windows.
| 01/18/2018 08:01 PM UTC |
CP002324 - Utilities-Chilled Water West Campus Distribution Improvements
The project consists of, but is not limited to, installing new underground utilities consisting of 24 inch chilled water supply and return piping, 12 inch to 42 inch storm sewer system with associated roadway intakes, 10 inch domestic water main, 10 inch sanitary sewer, a steam tunnel extension and underground electrical system for site lighting all under Bissell Road and the adjacent sidewalks from Osborn Drive to Union Drive. Additionally the project includes complete replacement Bissell Road, adjacent sidewalks and all new site lighting for areas affected by the underground utilities.
| 01/18/2018 08:01 PM UTC |
CP002415 - Veterinary Medicine-Stereotactic Radiation Therapy Addition
The project consists of, but is not limited to, demolition of existing partitions, mechanical, electrical and plumbing modifications, ceiling, lighting, flooring, new partitions, site utility modifications, and installation of a concrete footing system.
| 01/11/2018 08:01 PM UTC |
CP002387 - Utilities-Lied Recreation Athletic Facility-Steam Supply Replacement
The project consists of, but is not limited to, demolition of existing steam service associated equipment and piping. Installation of new interior gas distribution, gas fired boilers, heating piping, reheat water circulation system, pumps, and misc. electrical and general construction.
| 01/09/2018 08:01 PM UTC |
CP002355 - Wallace and Wilson Residence Halls-Window Replacement-Phase 2
The project consists of, but is not limited to, provide operable and fixed aluminum-framed windows with trim package as indicated in drawings in dens and select student rooms in Wallace and Wilson Residence Halls. The work includes ten residential floors, the mezzanine and the ground floors in each of the two buildings.
| 01/04/2018 08:01 PM UTC |
CP002437-Linden Residence Hall-Window Replacement
The project consists of, but is not limited to, providing new aluminum windows throughout building to replace existing windows removed under separate abatement contract, exceptions noted. Provide complete removal and replacement of exterior entrance assemblies. New aluminum entrance assemblies to include new hardware.
| 12/19/2017 08:01 PM UTC |
CP002343 - Institutional Roads 2018-Union Drive & Welch Road Reconstruction
The project consists of, but is not limited to, full roadway reconstruction of Union Drive and Welch Road, between Lincoln Way and Bissell Road on the Iowa State University campus. Work to be completed includes full-depth pavement reconstruction, curbs, pedestrian sidewalks and ramps, minor parking lot improvements, storm sewer piping and structures, pavement markings and street lighting.
| 12/19/2017 08:01 PM UTC |
CP002277-Richardson Court Residence Halls-Bathroom Remodeling-Phase 2-Issuance 2-BID PACKAGE 2.01-GENERAL CONSTRUCTION (PHASE 2B)
A. The project consists of, but is not limited to, the interior demolition, reconfiguration and remodeling of restrooms at Roberts and Lyon Residence Halls.
B. Issuance 2: Some of the bid packages have been divided amongst pairs of buildings to provide some division of the amount of work. “Phase 2B” will generally include work for the respective scope in Roberts and Lyon Halls. The “Phase 2B” work associated with Issuance 2 would be completed simultaneously with the previous Issuance 1 “Phase 2A” and Issuance 1 “Phase 2A & 2B” work.
| 12/14/2017 08:01 PM UTC |